Clevedon School Learning Village
08-12-2023
Fineline Lighting’s Rapid Deployment of Temporary Classrooms at Clevedon School
Clevedon School were facing immediate challenges due to the deterioration of Reinforced Alkali-Activated Concrete (RAAC) in its existing buildings and sought a rapid and effective solution to ensure the safety of students and staff. This case study explores the swift deployment of temporary classrooms by Fineline Lighting, showcasing their ability to respond urgently to infrastructure needs while maintaining high standards of safety and functionality.
Background;
The identification of RAAC-related issues in Clevedon School's buildings prompted the need for urgent action to relocate students and staff. Acknowledging the critical nature of the situation, the school administration collaborated with Fineline Lighting to deploy temporary classrooms as a quick and efficient solution.
Objective The primary objective of Fineline Lighting was to provide Clevedon School with temporary classrooms that could be rapidly deployed, meeting safety standards and providing a conducive learning environment for students.
Rapid Deployment Process;
Needs Assessment: Fineline Lighting conducted a thorough needs assessment in collaboration with Clevedon School and Futura Learning Partnership Trust to understand the space requirements, safety standards, and logistical considerations.
Design and Planning: Leveraging their expertise in events and temporary structures, Fineline Lighting proposed temporary classrooms solution using event marquee structures to meet the specific needs of Clevedon School, ensuring a seamless transition.
Logistics and Installation: Fineline Lighting coordinated the logistics for transportation and on-site installation, ensuring minimal disruption to the ongoing activities at the school. The modular nature of the classrooms facilitated swift assembly.
Safety Protocols: Rigorous safety protocols were implemented throughout the deployment process, ensuring the safety of students, staff and contractors whilst also ensuring that the temporary classrooms met or exceeded the identified safety standards.
Outlook of Temporary Classrooms;
Marquee Structure Design: The temporary classrooms were designed using marquee structures, allowing for quick assembly and disassembly as needed.
Amenities: Despite their temporary nature, the classrooms were equipped with essential amenities, including heating, ventilation, and lighting, to create a comfortable and functional learning environment.
Accessibility: The design ensured that the temporary classrooms were accessible to all students, including those with disabilities, promoting inclusivity.
Results;
The rapid deployment of temporary classrooms by Fineline Lighting at Clevedon School yielded several positive outcomes:
Immediate Relief: The temporary classrooms provided an immediate solution, allowing students and staff to transition swiftly from the affected buildings.
Continuity in Education: The quick deployment ensured minimal disruption to the learning process, maintaining the quality of education for students.
Adherence to Safety Standards: The temporary classrooms met stringent safety standards, providing a safe, secure, and comfortable environment for all occupants.
Conclusion: Fineline Lighting's rapid deployment of temporary classrooms at Clevedon School exemplifies their commitment to providing agile and effective infrastructure solutions. This case study serves as a model for educational institutions navigating time-sensitive challenges, showcasing the successful implementation of temporary structures without compromising safety or functionality.
Client Feedback;
Jim Smith, Head Teacher at Clevedon School commented…
“Fineline delivered a solution that works, is dry and warm (which was a main concern) and has meant we have been able to keep all our students in school learning.
Their experience from working with clients who need something to be ready at an exact time and to an exact specification was evident as they provided the perfect one-stop shop from design and procurement to installation and handover with all the necessary health and safety requirements expected of the school.
As a result of excellent communication, sage guidance and using an on-site Project Manager, they have been exceptionally easy to work with, delivered the solution with zero impact on school life and gone above and beyond to make our Learning Village a place where people want to be!”
Posted in: